<!------------- Equipment Status ----------------> |
<!------------- Equipment Status ----------------> |
||
− | ===== N2 Dry Box Cleanout, February 14th ===== |
||
− | We will be cleaning out the large N2 dry box next to the ASML. Anything with a label that's older than 2 months will be removed. As a reminder, the dry box is for active processing only. If you would like to store anything in a N2 only environment for greater than two months please use the vacuum sealer (in bay 4) or your own lab. Please let me know if you have any questions or concerns. |
||
− | [[User:Hopkins a|Hopkins a]] 16:07, 23 January 2020 (PST) |
||
===== GCA 6000 March Maintenance ===== |
===== GCA 6000 March Maintenance ===== |
||
Line 23: | Line 20: | ||
The Autostep 200 will be down for maintenance the morning of March 12, 2020 until late afternoon the same day. |
The Autostep 200 will be down for maintenance the morning of March 12, 2020 until late afternoon the same day. |
||
[[User:Silva|Silva]] 10:40, 10 February 2020 (PST) |
[[User:Silva|Silva]] 10:40, 10 February 2020 (PST) |
||
− | |||
− | ===== SignupMonkey Testing: Mon. Feb 17th, 7am ===== |
||
− | We will be running tests on the SignupMonkey servers at 7am on Friday Feb. 17th (delayed from previous). This may cause temporary outages of the server at this time. |
||
− | // [[User:John d|John d]] 10:52, 12 February 2020 (PST) |
||
===== ASML Maintenance: March 30th ===== |
===== ASML Maintenance: March 30th ===== |
Revision as of 15:00, 18 February 2020
Equipment Status
GCA 6000 March Maintenance
The GCA 6300 will be down for maintenance beginning 8:30am Monday March 9, 2020 until 6:30pm March 11, 2020. Silva 10:40, 10 February 2020 (PST)
GCA Autostep 200 March Maintenance
The Autostep 200 will be down for maintenance the morning of March 12, 2020 until late afternoon the same day. Silva 10:40, 10 February 2020 (PST)
ASML Maintenance: March 30th
ASML Stepper #3 periodic maintenance will be on Monday March 30th, system will be down for up to 1.5 weeks. // John d 07:30, 27 January 2020 (PST)
Unaxis ICP-PECVD
The ICP-PECVD module is down for general use. We are conducting experiments with the Deuterated Silane and are not allowing general use of the tool. Silva 15:04, 19 November 2019 (PST)
Suss Bonder
Suss Bonder is DOWN. The vendor is struggling to get the software and hardware upgrades to work. We have a meeting next week, 10/28/19, to discuss options. Silva 11:16, 25 October 2019 (PDT)