Template:Announcements

From UCSB Nanofab Wiki
Revision as of 11:16, 12 July 2023 by Mehalana v (talk | contribs)
Jump to navigation Jump to search

SEM announcement update
Once SEM 1 is up we’ll wait for at least a week before we decommission SEM 2.  

//Vraj Mehalana 11:16, 12 July 2023 (PDT)

Plasma Activation (EVG 810)

We have received almost all the replacement parts for the tool except the new chuck. The original delivery date of mid June has now been pushed out to early September and they have stated that this is the best that their supplier can do. I will not be installing any new parts on the tool until we have everything. Runs will still require Staff supervision until then. //Vraj Mehalana 18:01, 2 May 2023 (PDT)