<startfeed />
=====PlasmaTherm DSEIII is down - Update=====
 
  +
=====Atomic Force Microscope (Dimension ICON) - 05/08: AFM Head needs repair=====
We were able to start running recipes last night but we found the C4F8 MFC wasn’t controlling. I’ve ordered a new MFC that’s due to be on site Tuesday morning. If all goes well the tool should be up that afternoon.
 
  +
I will have to take the AFM head unit back to Bruker for repair. The height sensor failed all the tests I tried so the Z-piezo/strain gauge unit will most likely need to be replaced. SO for the foreseeable future, the AFM is down.--Demis
//[[User:John_d|Demis D. John]] 11:18, 23 February 2024 (PST)
 
   
 
//[[User:Mehalana v|Vraj Mehalana]] 13:42, 9 May 2024 (PDT)
=====ICP #1 is down - Update=====
 
 
=====MA6 TSA is down - Update=====
Some additional work is needed on the replacement board that we are waiting on. I have been informed that it will not be shipping until after the 20th (no solid date).
 
  +
Still waiting on a quote and lead time for the board we need for the TSA microscope issue, was supposed to have that info yesterday. I've just pinged them and will provide everyone with an update once I have something.
//[[User:John_d|Demis D. John]] 11:18, 23 February 2024 (PST)
 
   
 
//[[User:Mehalana v|Vraj Mehalana]] 11:15, 1 May 2024 (PDT)
=====RIE 5 is up=====
+
=====Velion FIB Tool DOWN=====
RIE 5 is up except for processes that use SiCl4.
 
  +
Raith service are installing and aligning a new GaBiLi source. The Velion FIB column is not available to users until further notice.
//[[User:Mehalana v|Vraj Mehalana]] 09:39, 30 January 2024 (PST)
 
   
 
//[[User:Mehalana v|Vraj Mehalana]] 10:58, 30 April 2024 (PDT)
=====EBeam3 Transfer Arm Upgrade - Postponed=====
 
The Transfer Arm upgrade has been postponed again, this time due to motor driver compatibility issues.
 
   
  +
=====ASML optics replacement May 20th-22nd=====
I am waiting to hear back from the manufacturer so at this time I can not reschedule yet.
 
  +
We will be performing beam delivery optics replacement on Mon May 20th to 22nd, to resolve a low intensity reading. The tool will be unavailable during this time.e.
   
  +
//[[User:Mehalana v|Vraj Mehalana]] 09:40, 9 May 2024 (PDT)
I will send another notification when everything has been worked out, and I am ready to schedule the installation.
 
//[[User:John_d|Demis D. John]] 11:56, 13 February 2024 (PST)
 
   
=====Job Opening: Process Engineer=====
+
=====ICP1 Down=====
  +
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
The Nanofab has a current job opening for a Process/Wafer-Fab Engineer, see the [https://wiki.nanofab.ucsb.edu/wiki/Nanofab_Job_Postings NanoFab Job Openings page] for details.
 
 
//[[User:Mehalana v|Vraj Mehalana]] 14:17, 1 March 2024 (PST)
 
//[[User:John d|Demis D. John]] 14:52, 30 October 2023 (PDT)
 
   
 
=====Lab Access Changes: Symmetry App=====
 
=====Lab Access Changes: Symmetry App=====

Latest revision as of 13:42, 9 May 2024

Atomic Force Microscope (Dimension ICON) - 05/08: AFM Head needs repair

I will have to take the AFM head unit back to Bruker for repair. The height sensor failed all the tests I tried so the Z-piezo/strain gauge unit will most likely need to be replaced. SO for the foreseeable future, the AFM is down.--Demis

//Vraj Mehalana 13:42, 9 May 2024 (PDT)

MA6 TSA is down - Update

Still waiting on a quote and lead time for the board we need for the TSA microscope issue, was supposed to have that info yesterday. I've just pinged them and will provide everyone with an update once I have something.

//Vraj Mehalana 11:15, 1 May 2024 (PDT)

Velion FIB Tool DOWN

Raith service are installing and aligning a new GaBiLi source. The Velion FIB column is not available to users until further notice.

//Vraj Mehalana 10:58, 30 April 2024 (PDT)

ASML optics replacement May 20th-22nd

We will be performing beam delivery optics replacement on Mon May 20th to 22nd, to resolve a low intensity reading. The tool will be unavailable during this time.e.

//Vraj Mehalana 09:40, 9 May 2024 (PDT)

ICP1 Down

The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps. //Vraj Mehalana 14:17, 1 March 2024 (PST)

Lab Access Changes: Symmetry App

Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. IMPORTANT: check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled "Invitation to Access Symmetry App". // John d 13:49, 7 November 2023 (PST)

Wafer Bonder, (Suss SB6-8E)

SUSS aims to be on site in early February. We’ll will send out an email once I get confirmation for a specific date. //Vraj Mehalana 14:23, 13 December 2023 (PST)