Difference between revisions of "Template:Announcements"

From UCSB Nanofab Wiki
Jump to navigation Jump to search
(28 intermediate revisions by 3 users not shown)
Line 1: Line 1:
 
<startfeed />
 
<startfeed />
=====E-Beam #4 (CHA) - EB4 Update=====
+
=====MA6 TSA is down - Update=====
  +
Still waiting on a quote and lead time for the board we need for the TSA microscope issue, was supposed to have that info yesterday. I've just pinged them and will provide everyone with an update once I have something.
After extensive troubleshooting it looks like the cryo pump will need to be replaced. We are hopeful the system will be ready to run sometime tomorrow early afternoon.
 
   
 
//[[User:Mehalana v|Vraj Mehalana]] 11:15, 1 May 2024 (PDT)
Tony
 
 
=====Velion FIB Tool DOWN=====
  +
Raith service are installing and aligning a new GaBiLi source. The Velion FIB column is not available to users until further notice.
   
//[[User:Mehalana v|Vraj Mehalana]] 18:55, 13 February 2024 (PST)
+
//[[User:Mehalana v|Vraj Mehalana]] 10:58, 30 April 2024 (PDT)
=====PECVD #2 is UP=====
 
The tool is up, intial film checks show same dep. rates as before.
 
//[[User:John_d|Demis D. John]] 11:56, 13 February 2024 (PST)
 
   
=====RIE 5 is up=====
+
=====Stepper #3 (ASML DUV) - PM Moved to 5/6 5/10=====
  +
We are postponing the Maintenance date to May 6th – 10th.
RIE 5 is up except for processes that use SiCl4.
 
  +
On the week of May 6th, ASML Engineers will be performing preventative maintenance, please plan your work around the tool being down at that time.
   
//[[User:Mehalana v|Vraj Mehalana]] 09:39, 30 January 2024 (PST)
+
//[[User:Mehalana v|Vraj Mehalana]] 09:42, 5 April 2024 (PDT)
   
  +
=====ICP1 Down=====
=====Dry Etch, Si Deep RIE (PlasmaTherm DSEIII) - DSE Update=====
 
  +
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
We received most of the chamber assembly replacement parts today. We are still waiting on the lamps and chamber o-rings which are scheduled to be delivered in the next couple of days. Once we have all the parts, we'll start to reassemble the chamber.
 
 
//[[User:Mehalana v|Vraj Mehalana]] 14:17, 1 March 2024 (PST)
 
I'll send out an update in the next 2-3 days.
 
 
Thanks,
 
//[[User:Mehalana v|Vraj Mehalana]] 10:58, 5 February 2024 (PST)
 
 
=====ICP #1 is down - Update=====
 
Replacing the battery on the board did not resolve the tool issue.
 
 
Panasonic has located a replacement board for the tool. From what I gather they need to repair and test it and are hoping to have it ready to ship by the 16th. I'd like to add that there is the possibility that this will not resolve the issue but it is the best path forward at this point.
 
 
-Lee
 
//[[User:Mehalana v|Vraj Mehalana]] 09:39, 30 January 2024 (PST)
 
 
=====EBeam3 Planned Maintenance 2/21/24 - 2/22/24=====
 
The transfer arm installation has been postponed until next week due to other equipment being down at this time.
 
 
The work is now scheduled for 2/21/24 - 2/22/24.
 
Please plan accordingly.
 
//[[User:John_d|Demis D. John]] 11:56, 13 February 2024 (PST)
 
 
=====Job Opening: Process Engineer=====
 
The Nanofab has a current job opening for a Process/Wafer-Fab Engineer, see the [https://wiki.nanofab.ucsb.edu/wiki/Nanofab_Job_Postings NanoFab Job Openings page] for details.
 
 
//[[User:John d|Demis D. John]] 14:52, 30 October 2023 (PDT)
 
   
 
=====Lab Access Changes: Symmetry App=====
 
=====Lab Access Changes: Symmetry App=====
 
Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. '''IMPORTANT''': check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled '''''"Invitation to Access Symmetry App"'''''.
 
Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. '''IMPORTANT''': check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled '''''"Invitation to Access Symmetry App"'''''.
 
 
// [[User:John d|John d]] 13:49, 7 November 2023 (PST)
 
// [[User:John d|John d]] 13:49, 7 November 2023 (PST)
   

Revision as of 11:15, 1 May 2024

MA6 TSA is down - Update

Still waiting on a quote and lead time for the board we need for the TSA microscope issue, was supposed to have that info yesterday. I've just pinged them and will provide everyone with an update once I have something.

//Vraj Mehalana 11:15, 1 May 2024 (PDT)

Velion FIB Tool DOWN

Raith service are installing and aligning a new GaBiLi source. The Velion FIB column is not available to users until further notice.

//Vraj Mehalana 10:58, 30 April 2024 (PDT)

Stepper #3 (ASML DUV) - PM Moved to 5/6 – 5/10

We are postponing the Maintenance date to May 6th – 10th. On the week of May 6th, ASML Engineers will be performing preventative maintenance, please plan your work around the tool being down at that time.

//Vraj Mehalana 09:42, 5 April 2024 (PDT)

ICP1 Down

The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps. //Vraj Mehalana 14:17, 1 March 2024 (PST)

Lab Access Changes: Symmetry App

Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. IMPORTANT: check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled "Invitation to Access Symmetry App". // John d 13:49, 7 November 2023 (PST)

Wafer Bonder, (Suss SB6-8E)

SUSS aims to be on site in early February. We’ll will send out an email once I get confirmation for a specific date. //Vraj Mehalana 14:23, 13 December 2023 (PST)