=====MA6 TSA is down - Update=====
  +
Still waiting on a quote and lead time for the board we need for the TSA microscope issue, was supposed to have that info yesterday. I've just pinged them and will provide everyone with an update once I have something.
   
 
//[[User:Mehalana v|Vraj Mehalana]] 11:15, 1 May 2024 (PDT)
=====Job Opening: Process Engineer=====
 
  +
=====Velion FIB Tool DOWN=====
The Nanofab has a current job opening for a Process/Wafer-Fab Engineer, see the [https://wiki.nanofab.ucsb.edu/wiki/Nanofab_Job_Postings NanoFab Job Openings page] for details.
 
  +
Raith service are installing and aligning a new GaBiLi source. The Velion FIB column is not available to users until further notice.
//[[User:Mehalana v|Vraj Mehalana]] 14:52, 30 October 2023 (PDT)
 
   
  +
//[[User:Mehalana v|Vraj Mehalana]] 10:58, 30 April 2024 (PDT)
=====EBeam2 UP=====
 
Test run completed without issue. System is ready to use, EXCEPT for heater - contact supervisor for heater use. See email for updates to operating procedure.
 
   
  +
=====Stepper #3 (ASML DUV) - PM Moved to 5/6 – 5/10=====
//[[User:Mehalana v|Vraj Mehalana]] 11:48, 26 October 2023 (PDT)
 
  +
We are postponing the Maintenance date to May 6th – 10th.
=====ProbeStation scheduled IT maintenance=====
 
The ProbeStation will be undergoing IT maintenance and will be unavailable on the following dates :
+
On the week of May 6th, ASML Engineers will be performing preventative maintenance, please plan your work around the tool being down at that time.
* 10-30-23
 
* 10-31-23
 
* 11-01-23
 
* 11-02-23
 
Please plan your work activities accordingly.
 
   
//[[User:Mehalana v|Vraj Mehalana]] 14:52, 30 October 2023 (PDT)
+
//[[User:Mehalana v|Vraj Mehalana]] 09:42, 5 April 2024 (PDT)
   
=====PECVD2 is down=====
+
=====ICP1 Down=====
  +
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
We were able to fix the vacuum leak but unfortunately the particulates are off the chart and rate is still a bit low. Tomorrow morning we will be taking the showerhead apart and cleaning it up before testing again.
 
//[[User:Mehalana v|Vraj Mehalana]] 16:48, 31 October 2023 (PDT)
+
//[[User:Mehalana v|Vraj Mehalana]] 14:17, 1 March 2024 (PST)
   
  +
=====Lab Access Changes: Symmetry App=====
=====Unaxis VLR - GapFill allowed Mon 30th 5pm to Wed 6am=====
 
  +
Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. '''IMPORTANT''': check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled '''''"Invitation to Access Symmetry App"'''''.
We are still working on an improved GapFill recipe.
 
  +
// [[User:John d|John d]] 13:49, 7 November 2023 (PST)
 
To allow your processes through, on Monday EVENING at 5pm we will allow the old "450W GapFill" recipe to be run,
 
 
- starting Monday Oct 30th, evening at 5pm,
 
 
- ending Wed Nov 1st, morning at 6am.
 
 
Reminder: You may NOT run the 450W recipe outside these allowed times, and you may Not modify our recipes apart from Dep/Clean TIME.
 
 
Let me know if you have any questions.
 
 
//[[User:Mehalana v|Vraj Mehalana]] 09:55, 11 October 2023 (PDT)
 
   
 
=====Wafer Bonder, (Suss SB6-8E)=====
 
=====Wafer Bonder, (Suss SB6-8E)=====
The top heater has failed. We are currently in the process of trying to source a new heater. we will send out an email once I have an update.
+
SUSS aims to be on site in early February. We’ll will send out an email once I get confirmation for a specific date.
 
//[[User:Mehalana v|Vraj Mehalana]] 14:23, 13 December 2023 (PST)
   
//[[User:Mehalana v|Vraj Mehalana]] 09:59, 20 September 2023 (PDT)
 
 
=====EVG Activation: Up=====
 
The FSE has completed the work on the tool and I have made several test runs without issue.
 
 
IMPORTANT - Please see corresponding email for changes in operation.
 
 
//[[User:Mehalana v|Vraj Mehalana]] 15:58, 24 October 2023 (PDT)
 
 
<!--
 
<!--
 
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
 
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
Line 55: Line 33:
 
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
 
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
 
-->
 
-->
<!---------------------------------------------->
 
<!------------- Equipment Status ---------------->
 
 
 
<!---------- end of Equipment Status ------------>
 
 
<!---------DO NOT EDIT BELOW THIS LINE----------->
 
<!---------DO NOT EDIT BELOW THIS LINE----------->
 
<endfeed />
 
<endfeed />

Revision as of 11:15, 1 May 2024

MA6 TSA is down - Update

Still waiting on a quote and lead time for the board we need for the TSA microscope issue, was supposed to have that info yesterday. I've just pinged them and will provide everyone with an update once I have something.

//Vraj Mehalana 11:15, 1 May 2024 (PDT)

Velion FIB Tool DOWN

Raith service are installing and aligning a new GaBiLi source. The Velion FIB column is not available to users until further notice.

//Vraj Mehalana 10:58, 30 April 2024 (PDT)

Stepper #3 (ASML DUV) - PM Moved to 5/6 – 5/10

We are postponing the Maintenance date to May 6th – 10th. On the week of May 6th, ASML Engineers will be performing preventative maintenance, please plan your work around the tool being down at that time.

//Vraj Mehalana 09:42, 5 April 2024 (PDT)

ICP1 Down

The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps. //Vraj Mehalana 14:17, 1 March 2024 (PST)

Lab Access Changes: Symmetry App

Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. IMPORTANT: check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled "Invitation to Access Symmetry App". // John d 13:49, 7 November 2023 (PST)

Wafer Bonder, (Suss SB6-8E)

SUSS aims to be on site in early February. We’ll will send out an email once I get confirmation for a specific date. //Vraj Mehalana 14:23, 13 December 2023 (PST)