The current schedule to replace SEM #2 is set to begin Monday the 31st of July.
Once SEM 1 is up we’ll wait for at least a week before we decommission SEM 2.
 
  +
We will begin decommissioning the tool that morning. Please plan accordingly.
//[[User:Mehalana v|Vraj Mehalana]] 11:16, 12 July 2023 (PDT)
 
  +
The new SEM #2 installation completion is still TBD. We will update you all as progress is made.
 
//[[User:Mehalana v|Vraj Mehalana]] 16:21, 24 July 2023 (PDT)
  +
 
=====Plasma Activation (EVG 810)=====
 
=====Plasma Activation (EVG 810)=====
 
We have received almost all the replacement parts for the tool except the new chuck. The original delivery date of mid June has now been pushed out to early September and they have stated that this is the best that their supplier can do. I will not be installing any new parts on the tool until we have everything.
 
We have received almost all the replacement parts for the tool except the new chuck. The original delivery date of mid June has now been pushed out to early September and they have stated that this is the best that their supplier can do. I will not be installing any new parts on the tool until we have everything.

Revision as of 16:21, 24 July 2023

Exhaust Fan Maintenance

Tomorrow (18 July) starting at 8 am we will be shutting down one of two exhaust fans for repair. There is a possibility that you will hear exhaust alarms on the process benches, but we will be in the lab to clear them and there should not be any impacts to operations. //Vraj Mehalana 16:34, 17 July 2023 (PDT)

SEM 1 Update

The field service engineer has finished with alignments and the SEM is up and running. The FSE will be back late Monday morning to do some fine adjustments. Please let us know if you encounter any issues. //Vraj Mehalana 16:36, 16 July 2023 (PDT)

SEM 2 Update

The current schedule to replace SEM #2 is set to begin Monday the 31st of July. We will begin decommissioning the tool that morning. Please plan accordingly. The new SEM #2 installation completion is still TBD. We will update you all as progress is made. //Vraj Mehalana 16:21, 24 July 2023 (PDT)

Plasma Activation (EVG 810)

We have received almost all the replacement parts for the tool except the new chuck. The original delivery date of mid June has now been pushed out to early September and they have stated that this is the best that their supplier can do. I will not be installing any new parts on the tool until we have everything. Runs will still require Staff supervision until then. //Vraj Mehalana 18:01, 2 May 2023 (PDT)