Equipment Status

Unaxis ICP-PECVD

The ICP-PECVD module is down for general use. We are conducting experiments with the Deuterated Silane and are not allowing general use of the tool. Silva 15:04, 19 November 2019 (PST)

Cleanroom Shutdown on 11/21

The cleanroom will be closed from 7-9am on Thursday, November 21st for fire system testing. No one will be allowed in the lab during this time. Please plan accordingly. Hopkins a 15:44, 6 November 2019 (PST)

Suss Bonder

Suss Bonder is DOWN. The vendor is struggling to get the software and hardware upgrades to work. We have a meeting next week, 10/28/19, to discuss options. Silva 11:16, 25 October 2019 (PDT)