===== Suss Bonder =====
 
===== Suss Bonder =====
  +
Suss fieldservice found several issues with the system. Suss will evaluate the issues and recommend possible solutions.
The system is down. We are waiting for fieldservce.
 
[[User:Silva|Silva]] 10:18, 4 February 2019 (PST)
+
[[User:Silva|Silva]] 21:36, 13 February 2019 (PST)
   
 
===== KLA Tencor Surfscan =====
 
===== KLA Tencor Surfscan =====

Revision as of 22:36, 13 February 2019

Equipment Status

Suss Bonder

Suss fieldservice found several issues with the system. Suss will evaluate the issues and recommend possible solutions. Silva 21:36, 13 February 2019 (PST)

KLA Tencor Surfscan

The system is down. The vendor has located a replacement PCB. Once the board is secured, the vendor will schedule a visit and finish the system repairs. Silva 21:51, 11 February 2019 (PST)

ALD Metal Dep

The system is down. A turbo pump has been sourced, and should be here Thursday February 14th. Silva 21:45, 11 February 2019 (PST)

E-Beam#1

The system is down. The E-Beam#1 power supply and control upgrade started today. We hope to complete the process within 10 business days. We will keep you posted as progress is made. Silva 21:45, 11 February 2019 (PST)

Vapor HF Etch

The system is down. The HF bottle is empty. The bottle will be replaced Wednesday February 13th. Silva 21:45, 11 February 2019 (PST)