<!------------- Equipment Status ---------------->
 
<!------------- Equipment Status ---------------->
  
===== Thermal Evap #1: DOWN =====
+
===== ASML: Down on Dec 12th =====
We are waiting for parts to come in to complete the repair on the Bell Jar hoist.
+
On Dec 12th the system will be down for half a day, so we can perform periodic maintenance (PM) on the DUV Laser.
We will notify once the system becomes available for use.
+
// [[User:John d|John d]] 16:47, 28 November 2022 (PST)
// [[User:John d|John d]] 17:06, 3 October 2022 (PDT)
 
  
===== E-Beam#2: Heater Down =====
+
===== Au Plating: DOWN =====
EB2 Heated Processing is down
+
Bath damaged, system is down for repair.
// [[User:John d|John d]] 15:40, 21 September 2022 (PDT)
+
// [[User:John d|John d]] 08:48, 27 October 2022 (PDT)
  
===== MLA 150 Service & Software Revision =====
+
===== E-Beam#2: Heater UP =====
 +
We tested the heater to 680°C three times without any issues. There is still the issue with the temp controller not communicating with the software which will get sorted out eventually. In the meantime you will just change the temp using the controller, directions are posted at the tool.
 +
// [[User:John d|John d]] 15:55, 6 December 2022 (PST)
  
The MLA will be down beginning the evening of Monday October 3rd and should be back up sometime Friday October 7th.
+
===== NanoFab Job Openings =====
// [[User:Sawyer l|L Sawyer]] 13:32, 31 August 2022 (PDT)
+
The NanoFab has current job openings, apply at: [https://wiki.nanotech.ucsb.edu/wiki/Nanofab_Job_Postings '''NanoFab Job Postings''']
  
===== ASML Up; Network status =====
+
// [[User:John d|John d]] 23:55, 4 October 2022 (PDT)
 
 
Nanofiles sync & JobCreator functionality is in the process of being restored.
 
Batch_Report syncing is not yet working. JobCreator is working with staff intervention, as local scripts are still being written + tested.
 
 
 
// [[User:John d|John d]] 15:44, 29 September 2022 (PDT)
 
  
 
<!---------- end of Equipment Status ------------>
 
<!---------- end of Equipment Status ------------>
Line 44: Line 40:
  
  
====== HOW TO ADD NEWS ITEMS ======
+
====== HOW TO ADD ITEMS ======
  
 
* You can copy/paste the example below for a new news item.
 
* You can copy/paste the example below for a new news item.

Latest revision as of 15:55, 6 December 2022

Important Announcements


ASML: Down on Dec 12th

On Dec 12th the system will be down for half a day, so we can perform periodic maintenance (PM) on the DUV Laser. // John d 16:47, 28 November 2022 (PST)

Au Plating: DOWN

Bath damaged, system is down for repair. // John d 08:48, 27 October 2022 (PDT)

E-Beam#2: Heater UP

We tested the heater to 680°C three times without any issues. There is still the issue with the temp controller not communicating with the software which will get sorted out eventually. In the meantime you will just change the temp using the controller, directions are posted at the tool. // John d 15:55, 6 December 2022 (PST)